Monday, March 31, 2014

Painting Crown Moulding and Ceilings


We bought MDF moulding with primer to save time with the finish painting.  When we started to lay them out for a coat of final paint, we found the surfaces were rough so we started early in the morning by lightly hand sanding 1600 linear feet of crown moulding.
We then laid them out all along the back of the shop so they could be painted using a sprayer.
 
 
We covered the back wall of the shop to prevent overspray on the wall and we rigged up tarps overhead so the moulding would not be in the direct sun while painting or drying.




After the first coat of paint, Gerry and Cliff moved into the house to paint the ceilings.






 
We moved Fred outside so he would not be in the way or in all the paint spray in the air in the house.


Sunday, March 30, 2014

Time to Paint Primer Throughout the Entire House

First--thank goodness--we hired painters to spray and back roll the primer throughout the entire house.
 
 
I couldn't believe Cliff wore a short-sleeve shirt and shorts.  After painting all day, he had paint all over his arms and legs!

 
Gerry and Cliff (paint contractor) break for lunch:

 
Seeing all the walls one color really helped define the rooms. The house finally looked like a house on the inside.




 
 
I used paper bowls to mask the can light fixtures--fast and easy.
 
 

We also painted primer in the garage:



Using a very bright light, Gerry walked along all the walls and marked all the dents, flaws, etc. so he could fix them before the final painting started.  Again, this took him a couple months to complete.

 
It took months of sanding and fine tuning the finish because I wanted smooth walls:
 
 
 

 
 
 
All the corners throughout the house are bullnose instead of 90-degeee corners.  They are susceptible to dents so Gerry covered them with bondo to make them stronger.  It took a long time to prep and finish sand them.  Gerry made a sanding block the shape of the corner out of foam, then he used double-stick tape to affix the sandpaper to the block.  This gave him much better control over the shape of the corners as he sanded them smooth.
 
 
 
 
Fred supervised , as always!



 



The Central Heating Unit

The central heating unit was installed in the attic hanging from the roof rafters.
 
 
The fittings are various sizes and shapes
 
 
And Gerry had a few custom pieces made and then had to modify several of the heating ducts.
 
 
Then the fittings had to be assembled on the ?
 
 


 

The heating element was attached.

 
 
Then Gerry had to run the flexible ducting to each room: