Kenny is cutting out the frames for the two round windows that get installed in the studio:
Tuesday, October 11, 2011
October 10th - Kitchen Skylights Are Installed
The two skylights in the kitchen were installed today. They're covered in plastic until the roofing around them gets installed.
View from inside the kitchen. These skylights open.
October 9th - Camping in the master bedroom!
We had company from out of town stay overnight so we set them up in the trailer bedroom and on the fold-down couch. We set up an air bed in the master bedroom for ourselves. (My other option was to sleep under the stars on the roof of the studio. I think I'll save that experience for a warm, summer evening next year!)
Sept. 21st - Oct. 8th What's been happening for the past two weeks?
I was sick for several days while the roofing on the house continued. All but the roof over the kitchen is complete--we're waiting for the two skylights to be delivered.
Gerry went on vacation to visit his nephew in Tahoe and his brother in Seattle. Before he left, rain was in the forcast, so he boarded up all the windows and wrapped the entire house and studio in plastic to keep the insulation dry.
Gerry went on vacation to visit his nephew in Tahoe and his brother in Seattle. Before he left, rain was in the forcast, so he boarded up all the windows and wrapped the entire house and studio in plastic to keep the insulation dry.
We had some rain come in over the kitchen. I could not find where the water had leaked in.
And this drop...out of nowhere!